Opening snapshot
Hundreds of Canning Town households left their homes overnight in October, a tribunal handed Urban Splash a £46.5m bill, and a new Bill is writing resident communication into law. The message this month is simple: what residents are told, and when, is a key component of compliance.
Regulatory update
The Remediation of Unsafe Cladding Bill passed second reading on 27 October. For residents, the headline is the Remediation Compliance Plan. Where an external wall appraisal (FRAEW) recommends work, owners must publish a plan within 15 months of royal assent setting out the steps, the timetable and the responsible director, and proactively share it with residents and leaseholders. The cost of producing the plan cannot be recharged to qualifying leaseholders. The Bill also extends person-centred fire risk assessments into the flats of residents who need evacuation support, with their consent.
Ministers also announced plans to raise the leaseholder protection threshold for non-cladding costs from three properties to six, and to fund collectively owned and enfranchised buildings. These are proposals, not yet law.
Meanwhile, MHCLG’s five plain-language FRAEW guides, including one for residents, now sit alongside PAS 9980:2026 and set out how residents should be kept informed through the appraisal process.
Enforcement and decisions
On 5 November the First-tier Tribunal ordered Urban Splash and four associated companies to pay £46.5m towards fixing seven Manchester buildings, most of it reimbursing the Building Safety Fund. The sum was cut by 10% to reflect the government’s share of responsibility for the wider crisis. For residents asking who pays, the answer increasingly reaches beyond the original developer to its wider group.
In the Technology and Construction Court, Mulalley v Sto entered default judgment in a building liability order claim against Sto’s German parent, with the contribution to be assessed on a just and equitable basis.
On 11 November the Regulator of Social Housing gave Bury Council a C3 grade, citing more than 2,800 overdue fire safety actions and limited evidence that tenants could influence services.
In practice
Canning Town is this month’s cautionary tale. Structural concerns surfaced while a building safety case was being prepared, residents were evacuated with little notice and were initially told to fund their own accommodation. Developer Galliard’s reimbursement offer followed about two weeks later. As a practical step, it is good practice for every owner of a higher-risk building to have an emergency communications plan ready for use before it is needed covering who tells residents, what support is available and a clear communications cascade and timetable.
Government figures estimate that around 101,000 homes are in buildings of 11 metres and over with unsafe cladding where remediation work has not yet started. These are the residents who will receive Remediation Compliance Plans once the Remediation of Unsafe Cladding Bill becomes law. Owners do not need to wait for royal assent to start that conversation. Share a realistic timeline for the works, a named contact and a plain-English summary of the building’s fire risk appraisal of external walls (FRAEW). Take care with messages about cost, though. The wider leaseholder protections announced at second reading are still only proposals, so avoid telling leaseholders they are covered until the amendments have been made to the Bill.
Social landlords should also note that Awaab’s Law extends to fire and structural hazards from 30 November, including a written summary to tenants within three working days of an investigation.
One to watch
The Remediation of Unsafe Cladding Bill is now at committee stage which is due to finish its line-by-line scrutiny by 8 December after hearing evidence from experts and resident representatives on 12 November. Dame Judith Hackitt, whose post-Grenfell review shaped the Building Safety Act, told the committee that residents still lack certainty about whether their buildings need work, or what standard will apply. The government has promised amendments that would:
- extend cost protection to leaseholders who owned up to six properties on 14 February 2022, rather than three
- fund repairs in collectively owned and enfranchised buildings, where leaseholders own the freehold and currently fall outside the Act’s protections
- make construction product manufacturers contribute towards remediation costs
Once these amendments are made to the Bill, owners will know which leaseholders they can tell, with confidence, that they will not pay. Until the committee finishes, it is still accepting written evidence at scrutiny@parliament.uk, so resident groups and landlords with first-hand experience still have a short window to be heard.
As ever, if any of this raises questions about how you communicate with stakeholders in your projects or portfolio, please do get in touch.
The Keeble Brown team
Disclaimer: This newsletter is produced for general information purposes only and does not constitute legal or business advice. Whilst we take care to ensure accuracy, the building safety regulatory landscape changes rapidly and readers should not act on the contents of this newsletter without taking specific legal or professional advice appropriate to their circumstances. Keeble Brown accepts no liability for any loss arising from reliance on the information contained herein. If you would like to discuss any of the issues raised, please contact us directly.